88 Energy says all systems go at Charlie-1

By Trevor Hoey. Published at Nov 27, 2019, in Energy

88 Energy Limited (ASX:88E) has provided an update ahead of the upcoming drilling of the Charlie-1 appraisal well at Project Icewine, located on the Central North Slope, Alaska.

Management confirmed that all conditions precedent to the farm-out agreement between 88 Energy, Premier and Burgundy Xploration signed in August 2019 had been satisfied and that execution of the final agreements took place on November 26, 2019.

Dealings with regulatory authorities are also progressing well.

The Alaska Department of Natural Resources approved the Plan of Operations for the Charlie-1 appraisal well last week.

The Plan of Operations is one of the key major permits required for drilling.

The final major permit is scheduled for submission in December, with approval expected in January ahead of the scheduled February spud date.

All other contracting and logistical work is proceeding as planned ahead of the scheduled February 2020 spud date.

Contracting and logistical work is proceeding as planned.
Contracting and logistical work is proceeding as planned.

88 Energy expects new technology to yield success at Charlie-1

The Charlie-1 appraisal well has been designed as a step out appraisal of a well drilled in 1991 by BP Exploration (Alaska) Inc called Malguk-1.

From a geological perspective, Malguk-1 encountered oil shows with elevated resistivity and mud gas readings over multiple horizons during drilling, but it was not tested due to complications towards the end of operations, which resulted in a lack of time before the close of the winter drilling season.

It was also drilled using vintage 2D seismic, which was insufficient to adequately determine the extent of any of the prospective targets encountered.

88 Energy subsequently undertook revised petrophysical analysis, which identified what is interpreted as bypassed pay in the Malguk-1 well.

Management also acquired modern 3D seismic in 2018 in order to determine the extent of the discovered oil accumulations.

Charlie-1 to intersect seven stacked prospects

As indicated below, Charlie-1 will intersect seven stacked prospects, four of which are interpreted as oil bearing in Malguk-1 and are therefore considered appraisal targets.

Charlie-1 will intersect seven stacked prospects.
Charlie-1 will intersect seven stacked prospects.

88 Energy will operate Charlie-1, via its 100% owned subsidiary Accumulate Energy Alaska, Inc, with the cost of the well to be funded by Premier Oil Plc up to US$23 million under a recent farm-out agreement.

Drilling is scheduled to commence in February 2020 with flow testing anticipated to conclude in April 2020.

The total Gross Mean Prospective Resource across the seven stacked targets to be intersected by Charlie-1 is 1.6 billion barrels of oil, representing 480 million barrels net to 88E.

The total Gross Mean Prospective Resource across the seven stacked targets to be intersected by Charlie-1 is 1.6 billion barrels of oil.
The total Gross Mean Prospective Resource across the seven stacked targets to be intersected by Charlie-1 is 1.6 billion barrels of oil.

S3 Consortium Pty Ltd (CAR No.433913) is a corporate authorised representative of LeMessurier Securities Pty Ltd (AFSL No. 296877). The information contained in this article is general information only. Any advice is general advice only. Neither your personal objectives, financial situation nor needs have been taken into consideration. Accordingly you should consider how appropriate the advice (if any) is to those objectives, financial situation and needs, before acting on the advice.

Conflict of Interest Notice

S3 Consortium Pty Ltd does and seeks to do business with companies featured in its articles. As a result, investors should be aware that the Firm may have a conflict of interest that could affect the objectivity of this article. Investors should consider this article as only a single factor in making any investment decision. The publishers of this article also wish to disclose that they may hold this stock in their portfolios and that any decision to purchase this stock should be done so after the purchaser has made their own inquires as to the validity of any information in this article.

Publishers Notice

The information contained in this article is current at the finalised date. The information contained in this article is based on sources reasonably considered to be reliable by S3 Consortium Pty Ltd, and available in the public domain. No “insider information” is ever sourced, disclosed or used by S3 Consortium.

Thanks for subscribing!

X